Current Work Notices

Over the coming week (weather permitting) Council’s Civil Works section will be undertaking work activities at the following locations:

Weekly Current Works

20 March 2017

  • 14 Lonsdale Street, Lilyfield (24m2 Asphalt tree root repair)       
  • Thornley Street and Roseby Street, Leichhardt (46m2 Asphalt tree root repair)
  • Darley Street and Francis Street, Leichhardt (120m2 Asphalt tree root repair)
  • Corner of Terry Street and Bridge Street, Balmain (16m2 Asphalt road maintenance)
  • Albion Street, Annandale (16m2 Asphalt road maintenance)
  • Pritchard Lane, Annandale (26m2 Asphalt road maintenance)
  • 142 and 144 Johnston Street, Annandale (36m2 Concrete tree root repair footpath maintenance)
  • 126-132 Trafalgar Street, Annandale (46m2 Concrete tree root repair footpath maintenance)
  • 185 Nelson Street, Annandale (12m2 Concrete tree root repair footpath maintenance)
  • 46 Nelson Street, Annandale (16m2 Concrete tree root repair footpath maintenance)
  • 19 Beeson Street, Leichhardt (Stormwater repairs and/or kerb & gutter repairs)
  • Regent Street, Rozelle (Stormwater repairs and/or kerb & gutter repairs)
  • 51 Hay Street, Leichhardt (Maintenance Repairs/Upgrades)
  • 39 Norton Street, Leichhardt (Maintenance Repairs/Upgrades)
  • 134 Marion Street, Leichhardt (Maintenance Repairs/Upgrades)
  • 26 High Street, Leichhardt (Concrete vehicle crossing)
  • 25 John Street, Leichhardt (Asphalt Correction)
  • 531-563 Parramatta Road, Leichhardt
  • 463 Parramatta Road, Leichhardt
  • 59 and 61 Burfitt Street, Leichhardt (Asphalt correction)

    Any enquiries please contact Richmond Alcorn, Council’s Civil Works Coordinator on 9367 9020 between 7am – 3.30pm.

    Other Works     

    Road Resurfacing Program - Short Street, Leichhardt (Balmain Road to Norton Street)

    Council will be carrying out asphalt road resurfacing works in Short Street, Leichhardt scheduled for 1 day shift on Thursday 30th March 2017, weather permitting.
    Council's contractor will confirm the date prior to commencing works.  The work can get postponed for few days if it rains during the week.  Traffic control officers will be on site on the day before (from 4pm) confirming the date and requesting residents to move the car on the next day.
    Contact person: Sadat Rahman on 9367 9295.

    Cyclic Street Tree Maintenance Works

    Council's Tree Contractors AUTS (Australian Urban Tree Service) are commencing Cyclic Street Tree Maintenance in the Leichhardt LGA.
    Pruning works are scheduled on 20th March 2017 to 24th March 2017, in the following streets:

    • Edna Street, Lilyfield
    • Paling Street, Lilyfield
    • Ilka Street, Lilyfield
    • Lonsdale Street, Lilyfield
    • Russell Street, Lilyfield
    • Pretoria Street, Lilyfield
    • Ainsworth Street, Leichhardt
    The program has proved successful with the number of street tree complaints received being reduced and the appearance and amenity of the street being improved.

    Contact person: Heidi Webb on 9367 9219.

    Road Work at Catherine Street Leichhardt - (Parramatta Road to Albion Street on 23rd March 2017 - night shift; and Albion Street to Styles Street on 8th & 9th April 2017 - day shift)

    Council will be carrying out asphalt road resurfacing works in the street mentioned above on Thursday 23rd March 2017 (night shift) and 8th & 9th of April 2017 (weekend shift), weather permitting. 
    Council's contractor will confirm the date prior to commencing works.  The work can get postponed for few days if it rains during the week.  Parking patrol officers will be on site to barricade the work site on the day before starting the work and to notify the residents to move the cars on the next day.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - Bradford Street, Balmain (Booth Street to Jane Street) on Friday 24th March 2017

    Council will be carrying out asphalt road resurfacing works in the Bradford Street Balmain on Friday 24th March 2017, weather permitting.
    Work can get postponed for few days if it rains during the week.  Council contractor will confirm the date prior to commencing works.  Traffic patrol officers will be on site on the day before (from 4pm) confirming the date and requesting residents to move the car on the next day.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - Roseberry Street Balmain (Evans Street to Mullens Street)

    Council will be carrying out asphalt road resurfacing works in Roseberry Street Balmain on Wednesday 22nd March 2017, weather permitting.
    Council contractor will confirm the date prior to commencing works.  The work can get postponed for few days if it rains during the week.  Traffic patrol officers will be on site on the day before (from 4pm) confirming the date and requesting resident to move the car on the next day.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - Stewart Street Balmain (Mullens Street to Pashley Road); and Stewart Place Balmain (Stewart Street to End)

    Council is carrying out maintenance works in Stewart Street and Stewart Place, Balmain.
    Work is scheduled to commence on Monday 20th March 2017. The work can get postponed for few days if it rains during the week. Council's contractor will confirm the date prior to commencing works.
    Wok involves asphalt road maintenance.  The construction area will be barricaded and sign posted.
    Contact person: Sadat Rahman on 9367 9295.

    Footpath Work - Stanley Street Leichhardt (Balmain Road to MacKenzie Street)

    Council is carrying out reconstructing footpath on Stanley Street, Leichhardt from Balmain Road to MacKenzie Street.
    Work is scheduled to commence on Monday 20th March 2017 and should take two weeks to complete, weather permitting. 
    The contractor will confirm the specific date by letter before starting the work.
    Where grass verge is laid Council's contractor will maintain watering throughout the duration of works. Council would appreciate the residents watering the grass verge until it is established after the footpath works have been completed.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program :-
    Curtis Road, Balmain (Clayton Street to McDonald Street) - 14/03/2017
    Thames Street, Balmain (Curtis Road to Trouton Street) - 14/03/2017
    Curtis Road, Balmain (Church Street to Mort Street) - 15/03/2017
    Phillip Street, Balmain (Curtis Road to Cameron Street) - 15/03/2017

    Council is carrying out maintenance works in the streets mentioned above on Tuesday 14 March 2017 and Wednesday 15 March 2017, weather permitting. 
    The work can get postponed for few days if it rains during the week.  Council's contractor will confirm the date prior to commencing works.
    Work involves asphalt road maintenance. The construction area will be barricaded and sign posted.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - Rowntree Street, Balmain (Spring Street to Curtis Road) ; and Bay Street, Balmain (Rowntree Street to Short Street)

    Council is carrying out maintenance works in Rowntree Street and Bay Street, Balmain.
    Work is scheduled to commence on Thursday 16 March 2017, weather permitting.  Council's contractor will confirm the date prior to commencing works.
    Work involves asphalt road maintenance. The construction area will be barricaded and sign posted.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - Theodore Street, Balmain (Montague Street to End)

    Council is carrying out maintenance work in Theodore Street, Balmain.
    Work is scheduled to commence on Friday 17 March 2017, weather permitting.  Council's contractor will confirm the date prior to commencing works.
    Work involves the restoration of asphalt road. The construction area will be barricaded and sign posted.
    Contact person: Sadat Rahman on 9367 9295.

    Road Resurfacing Program - St Marys Street Balmain East and Johnston Street Balmain East

    Council is carrying out maintenance work in St Marys Street Balmain East (Pearson Street to William Street); and Johnston Street Balmain East (Darling Street to Pearson Street).
    Work is scheduled to commence on Tuesday 7 March 2017 in St Marys Street and on Monday 13 March 2017 in Johnston Street, weather permitting.
    Work involves asphalt road maintenance.  The construction area will be barricaded and sign posted.
    Contact person: Sadat Rahman on 9367 9295.

     

      If you would like to report any issues or problems in your street use the Snap Send Solve App to let Council know. 

    Alternatively you can complete the Request a Service/Report an Issue online form.